Things are moving along well at our Surfleet Road development. All trades are pushing hard, and we’re lucky to have such a great team of subcontractors on site keeping everything moving forward.
The weather hasn’t made life easy lately, with snow and rain causing the odd slowdown, but despite that, progress continues across the site.
✔️ All timber frames are now fully erected, with roof coverings installed.
✔️ Brickwork is underway on the final 8 plots and is forecast to complete by mid-February.
✔️ First fix plumbing is complete in 28 plots, with the remaining plots also targeted for mid-February.
✔️ First fix carpentry is complete on plots 31–37 and 1–12, and ongoing across the rest of the site.
✔️ First fix electrics are nearly finished, with just 4 plots left to complete.
✔️ Second fix electrics are complete on plots 31–37 and ongoing on plots 1–7.
✔️ Kitchens are fitted on plots 31–37, with plots 1–7 scheduled for early February.
A big thank you to everyone on site for their continued hard work — we’ll keep sharing updates as things progress.
Glen Smith – Site Manager